Operational Impact

USD 100K

Estimated Cost Savings

55%

Improved Drilling Time

29

Rig States

Value Delivered

Event Summary

A U.S. operator was experiencing excessive non-productive time (NPT) during well construction due to inefficient drilling practices.
Offset well analysis revealed a consistent pattern: reaming and back-reaming were performed at every connection, despite no hole stability issues. This unnecessary activity added significant rig time and cost per well.

By deploying VuMaxPro’s real-time data integration with 29 rig states, the operator was able to:

VuMaxPro transformed unmeasured habitual behavior into actionable performance data driving measurable operational and financial gains.

Well Details

Region

US Operator

Rig Location

Land

Section

12.25”

Well Type

Directional